School
opens: September 2008 |
| • |
Principal: Eileen Moreno |
| • |
Status: Construction began
in December 2005.
|
| • |
Location: 4080 52nd Street, San Diego, CA 92105. City
Heights. The site is bound by property south of Orange
Avenue on
the north, Polk Avenue on the south, 52nd Street on the east, and
Altadena
Street on the west, and also includes the properties bound by Polk
Avenue
on the north, 52nd Street on the east, Ottilie Place on the south, and
51st Street on the west (a.k.a. Alternative Site A Expanded). |
| • |
Purpose:
Mary Lanyon Fay Elementary will ease overcrowding at Jackson
Elementary
and Marshall Elementary. It will also eliminate a student overflow
annex at Mann Middle School.
|
| • |
New school size: The new school will accommodate 700
students in grades K-5 on 6.3 acres.
|
| • |
Acquisition
and relocation: The
new school required the acquisition of 42 parcels, and the relocation
of 169
households consisting of 608 residents. Of the 169 households, 8 used
their
relocation funds to become first-time homeowners. |
| • |
Name of new
school: The school is named for a well-known civic leader and one
of the longest serving Board of Education members. Fay was appointed in
1937, served as president and vice president for 18 years, and
advocated for the hiring of the first African-American teachers.
|
| • |
Campus
features: 32
classrooms, 61,000 square feet of facilities, 6.3 acres, 58 parking
spaces, 65
trees, numerous shrubs, joint-use field for soccer and baseball,
multipurpose room, library/media center, lunch
shelter, elevator and accessibility features, kitchen, faculty lounge,
workroom, administrative center, and energy-efficient design
features. |
| • |
Project
partners: douglas e. barnhart and Mesquita & Associates
|
| • |
Project
milestones:
• Proposition
MM approved: November 3, 1998
• Draft
Environmental Impact Report: November 15, 2002
• Board
of Education approves site: June 10, 2003; August 5, 2003
• Community
names school: November 18, 2003
• Contract
awarded: November 8, 2005
• Groundbreaking
ceremony: March 30, 2006
• First
day of school: September 2007
|
| • |
Media
releases | Special
events | Fact sheet |
| • |
Site
map |
| • |
Artist's rendering | Site layout |
| • |
Property
parcel map with addresses |
| • |
Final
Environmental Impact Report |
| • |
Final
Environmental Impact Report Addendum |
| • |
Draft
Relocation Plan: English
| Spanish |
| • |
Board
of Education Report, June 10, 2003 |
| • |
Board
of Education Report, August 5, 2003
|