School
opens: OPEN! March
2006 |
| • |
Principal: Carolanne
Buguey
|
| • |
Status: Construction is completed.
|
| • |
Location: 401 45th
Street, San
Diego, CA 92102. Chollas View. The district-owned site is just
south and west of the existing
Chollas
Elementary. |
| • |
Purpose:
Mead Elementary has been rebuilt due to deterioration, enrollment
growth
and irregular grade configurations. It has also eased overcrowding at
Chollas
Elementary. |
| • |
New school size: The rebuilt school
can accommodate 450 students on 7.2 acres. |
| • |
Acquisition
and relocation: Not required. Under Proposition MM, the old Mead
Elementary
was to be demolished, rebuilt and expanded. Because expansion would
have
required the demolition of 18 homes and relocation of residents, the
new
Mead Elementary was instead built on seven acres of district-owned
property adjacent to Chollas Elementary. This action saved $10 million,
preserved affordable housing and avoided displacement of students
during
construction. The old Mead Elementary will possibly be leased or sold. |
| • |
Name of school:
The school will retain the name of Mead Elementary, in
honor of Francis Mead.
|
| • |
Campus features: 22 classrooms, 47,596
square feet of facilities,
7.2 acres, 66 parking spaces, joint-use field for soccer and baseball,
multipurpose room, library/media center, lunch shelter, elevator and
accessibility features, kitchen, faculty lounge, workroom,
administrative
center, and energy-efficient design features. The project also includes
a new
4,778-square-foot Child Development Center. |
| • |
Project
partners: C.E. Wylie Construction and R.J. Maus Architects |
| • |
Project
milestones:
• Proposition
MM approved: November 3, 1998
• Draft
Environmental Impact Report: October 18, 2002
• Board
of Education approves site: February 4, 2003
• Contract
awarded: May 25, 2004
• Groundbreaking
ceremony: July 9, 2004
• First
day of school: March 2006
|
| • |
Media
releases | Special
events | Fact sheet |
| • |
Site
map |
| • |
Artist's renderings: Building
200 | Child Development Center | Site layout
|
| • |
Final
Environmental Impact Report |
| • |
Board
of Education Report, February 4, 2003
|